Building regulations inspections
The Building Regulations set out requirements for specific aspects of building design and construction. Building regulations approvals can be sought either from the building control department of the local authority or from an approved inspector. The approval may involve desk studies to verify submitted information and / or inspections.
Very small projects and changes to an existing buildings can obtain building regulations approval purely by inspection. Larger, new-build projects, will generally require a 'full plans' application, meaning that full details of the proposed building works are submitted for approval before the works are carried out, and then inspections are carried out to ensure that the works have been undertaken in accordance with the approved information.
The number and frequency of inspections will depend on the nature of the works being undertaken. Typically they will take place at key stages such as:
- Commencement.
- Excavation, (before excavations are filled).
- Foundations (before they are covered up).
- Laying of damp proof courses.
- Installation of new drains (before covering up).
- Construction of the primary structure.
- Installation of insulation.
- Roof construction.
- Completion.
Advance notice of the progress of the works must be given to the relevant building control body so that they are able to schedule inspections at the appropriate times. If the appropriate inspections have not been carried out, a completion certificate may not be issued, and it may be necessary to open up parts of the works so that inspections can be carried out.
NB: Competent person self-certifications schemes (or competent person schemes) introduced in 2002 allow registered installers (mostly small firms or sole traders) who are competent in their field to self-certify certain types of building work. See Competent person self-certifications schemes for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Download your free guide.
Four new types of prior approval for solar developments
Online Planning Portal application types from 5 September.
Election fails to spark construction industry revival
Contract awards and planning; post election.
Making diversity and inclusion easy for SMEs
The CIOB tool for companies with limited resources.
Sustainable Futures: Redefining Retrofit for Net Zero Living
BSRIA Briefing 2024, initial speakers announced.
Looking back at the UK's first Passivhaus leisure centre
Reflections on St Sidwell’s Point with CIAT.
A-Level results and electrical apprenticeships
Electrical Skills Index highlights areas with skills shortages.
One of the world's more unusual drive-throughs.
A quick introduction.
Hadrian's Wall Path and the national trails
The trails are heritage assets in their own right.
Articles on timely advice and hydraulic lime.
Building Designers Association of Australia
CIAT and BDAA sign Memorandum of Understanding.
Built Environment Inclusive partners issue statement committed to inclusion.
Building regulation requirements can have unintended consequences.
CIOB announces 2024/25 vice president
Sustainability champion Professor Saul Humphrey.
Accelerating towards a net-zero built environment.